Getting a little closer everyday. Somedays it feels like we have been at this forever and other times it seems to be going quickly. Now that the drywall is up and taped they are working on getting everything textured.
Its so nice to see things starting to get painted. It seems like such a final step and so much closer to being done.
These stairs were such a pain in the butt. They each had to be built twice because they were put in wrong. It was very frustrating but as you can see Milo now agrees they are right!
I am loving the accent that these faux beams are adding to the space. It was something we wished we had done in the firt house so Im happy we are getting to do them now.
Tile is making great progress and turning out really well. First its hard to pick tile you like and blends together...then you have to pick grout. We decided to go with dark grout so it would be easier to clean.
They delivered all of the cabinets but started with the bathrooms. They seem to go in pretty quickly
The gym is becoming very handy for quite a few things. The cabinet guys put all of the basement cabinets in the gym so they wouldn't be in the way for painting.
Its so nice to pull into the house and find people here working.
Matt did an amazing job with the bunk room beds. They turned out just like we wanted
Reading nook. I really think this space will get used a lot. The girls have been really excited picking out lights. It was a great use of this space.
The basement family room doubles as lumber storage. Can't wait for the day when all of this is where it goes permantly in the house.
Basement laundry. I think this will get used a ton for wet towels, swimsuits, and snow closes that need a place to dry.
Decided to add some shiplap
Rock Prep
This weekend I was wracking my brain what I could do to help take things off Matt's to do list so I took on the mechanical room. I think it turned out pretty good
We finally got some snow...everyone is pretty thrilled about that